Metro Transit Center

Contract Amount = $5,322,000

As HVAC and Plumbing Contractor for the new METRO Downtown Transit Center & Administration Office Building project, Way Engineering furnished and installed the Central Plant, Air Conditioning, Heating and Plumbing Systems for this 14 Story, 380,000 square foot office building.

The Mechanical Scope included furnishing and installing (3) Chillers, (2) Cooling Towers, (60) Air Handlers and miscellaneous equipment for 1250 tons of cooling and 1298 MBTUH Heating. The Plumbing Scope of work included over 397 Plumbing fixtures. Our work on this project also included pipe, fittings, insulation and sheet metal work.

The METRO Downtown Transit Center & Administration Office Building was completed in February of 2005.